CONNECTION CONDITIONS

The procedure for obtaining grid connection conditions for installations requiring access to the power grid consists of several stages. Below is a detailed step-by-step description to help understand how this process works:

  1. Preparation of the grid connection conditions application

a. Gathering necessary data:

  • Exact location of the facility,
  • Estimated power demand,
  • Purpose of the facility (e.g., residential, industrial),
  • Contact information of the applicant.

b. Completing the appropriate form:

  • Filling out the official application provided by the distribution network operator (DNO) or chosen energy supplier. The application should contain all the above information and any additional documents required by the operator.
  1. Submission of the application

The application along with a complete set of documents should be submitted directly to the network operator, by traditional mail, email, or in person at the customer service office, depending on the preferences and requirements of the operator.

  1. Evaluation of the application by the network operator

a. Technical analysis:

  • The network operator conducts a technical analysis regarding the feasibility of connecting the facility to the grid. Aspects such as power availability in the area and necessary infrastructure modifications are considered.

b. Site visit:

  • In some cases, a site visit may be necessary to assess the terrain and technical conditions required for the connection.
  1. Receipt of grid connection conditions

Upon a positive evaluation of the application, the network operator issues grid connection conditions, which specify the technical and organizational requirements necessary for connecting the facility to the grid. This document includes:

  • Details regarding the connection point,
  • Required technical parameters of the installation,
  • Estimated costs of connection implementation,
  • Timeline for connection works.
  1. Acceptance of conditions and connection implementation

After receiving and accepting the grid connection conditions, the implementation works can commence according to the provided guidelines. Suitable technical teams and materials necessary for the connection must be organized.

  1. Technical inspections and finalization of the process

After the completion of installation works, technical inspections are carried out to confirm compliance with technical and safety requirements. Upon successful inspection, the installation can be officially connected to the grid, and the facility can start receiving energy supply.

  1. Documentation management

Throughout the process, meticulous documentation related to the connection implementation must be maintained, including correspondence with the network operator, a copy of the grid connection conditions, and documentation from technical inspections.

The process of obtaining grid connection conditions may vary depending on the project’s specifics, local regulations, and the network operator. It is essential to follow the guidelines provided by the operator and always act in accordance with applicable industry norms and standards.

BECOME A PARTNER OF THE ENERGY TRANSFORMATION

Contact us if you are interested in cooperation in the field of Energy Transformation.

PARTICIPANTS OF GREEN HUB PL

ML

AON

ELQ

BORGA

PEXPOOL

GREEN ENERGY

ZPUE

DACPOL

PODKARPACKA

IN LOGISTICS

COPADATA

Elektrometal

PowerBerry-en

EPS

ZPAS

Airpol

FREO

Prosta Kreska

BlueBoson

Śląska

KD&D

BaseID.eu

Rada Ekspertów

Green Power Solutions

ForumID.org

TVgreen.eu

Europerspektywy

Świat Elit

LEX